12 Miss. Code. R. 3-20-600.28 - ALLOWANCES
The Bureau discourages allowances unless absolutely necessary. Any allowance (i.e., brick, signage, special equipment, contingency, wall covering, carpet, etc.) should have prior approval from Bureau Staff before being incorporated in the Construction Documents:
1.
Contingency: Not
allowed.
2.
Brick: An
amount per thousand for purchase and delivery only is a normal, acceptable
practice.
3.
Hardware:
A hardware schedule will be included in the Contract Documents. If for some
reason, a hardware schedule is not included in the Bid Documents, after the
award of contract, the Professional must prepare a hardware schedule and secure
a minimum of three (3) proposals and award a subcontract to the lowest and best
bidder.
4.
Carpet: A
lump sum amount which includes carpet pad and installation, is acceptable. Unit
cost per square yard is discouraged. After the contract award, the Bureau will
select the carpet. The Professional will secure a minimum of three (3)
proposals and award a subcontract to the lowest and best bidder.
5.
Wall Covering: A lump sum
amount including delivery and installation is acceptable. Unit cost per roll or
square yard is discouraged. After the contract award, the Bureau will select
the wall covering. The Professional will secure a minimum of three (3)
proposals and award a subcontract to the lowest and best bidder.
6.
Signage: Not allowed unless
approved by Bureau Staff.
7.
Special Equipment: Not allowed unless approved by Bureau
Staff.