12 Miss. Code. R. 3-20-600.35 - CONSTRUCTION DOCUMENT REVIEW

The Professional, upon completion of the Construction Documents, will submit two (2) sets of drawings, two (2) Project Manuals and an updated estimate of cost to the Bureau. Note, the cost estimate should reflect the total budget including construction, furniture and equipment, fees and contingency. This same information will be furnished to the Using Agency, its Governing Board and for Review By Others (where applicable).

Notes

12 Miss. Code. R. 3-20-600.35
Adopted 11/25/2016 Amended 3/15/2021

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.