15 Miss. Code. R. 20-72-5.4.1 - General
Eligible costs are those costs in which ARPA RWAI Grant participation is authorized pursuant to applicable statute. Allowable costs are eligible costs that meet the following criteria:
1. Are necessary and reasonable for the
proper and efficient administration and construction of the project, are
allocable to and within the defined scope of the project and are not a general
expense required to carry out the overall responsibilities of the Grant
recipient.
2. Are authorized or not
prohibited under federal, state, or local laws or regulations.
3. Conform to any limitations or exclusions
set forth in state laws or other governing limitations as to types or amounts
of cost items.
4. Are consistent
with policies, regulations, and procedures that apply uniformly to both state
assisted and other activities of the Grant recipient.
5. Are accorded consistent treatment through
the application of generally accepted accounting principles appropriate to the
circumstances.
6. Are not allocable
to or included as a cost of any other Federal or State financed program in
either the current, prior, or future period.
7. Are approved as allowable by the
Department.
8. Are within the scope
and budget period of the project as per the Grant agreement. However, the
budget period does not apply to the planning and design allowance.
9. Notwithstanding this Subchapter, are
eligible and allowable under the ARPA and any implementing federal
regulations.
10. Are procured in
accordance with Subchapter 7 of these regulations.