18 Miss. Code. R. 17-4.6 - DECCD Application Processing

Applications cannot be approved until the application is complete. No application is complete until all required documentation has been submitted. The applicant must complete the application within sixty (60) days of application submission date.

Notes

18 Miss. Code. R. 17-4.6
45 CFR 98.33; Miss. Code Ann. § 43-1-2(4); Miss. Code Ann. § 43-1-4 Revised: March 2020
Adopted 3/6/2020 Amended 11/1/2021 Amended 5/15/2023

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.