19 Miss. Code. R. 5-7.04 - Grants
1. Eligibility. To be eligible for an SMH
grant, an applicant must meet the following requirements:
a. Homeowner must claim its primary residence
in a county where grants are being made available.
b. The home that is the subject of the grant
must be an owner occupied, single-family, primary residence, and cannot be a
condominium or mobile home.
c. The
home must be in good repair and insurable, unless damaged by a hurricane,
non-hurricane wind, or hail. SMH grant funds cannot be used for regular
maintenance or repairs but may be used in conjunction with repairs or
reconstruction necessitated by damages from a hurricane, non-hurricane wind, or
hail.
d. Homeowner must retrofit
the home to the Insurance Institute for Business and Home Safety (IBHS)
FORTIFIED RoofTM (Roof) or an IBHS successor
designation.
e. Homeowner must
provide proof of an in-force policy providing wind and hail insurance coverage
on the home.
f. If the home is in a
Special Flood Hazard area, homeowner must provide proof of an in-force flood
insurance policy. The flood policy may be from the National Flood Insurance
Program (NFIP) or a private carrier.
g. FORTIFIED projects must be completed
within three (3) months of the date of the notification of grant approval.
Failure to complete the project timely may result in the forfeiture of the
grant. The commissioner may grant a homeowner an extension of time to complete
the SMH project if an extension is timely requested in writing and the
homeowner provides sufficient proof that extenuating circumstances cause or
will likely cause delays in the completion of the SMH project. Whether to grant
or deny a request for an extension of time shall be subject to the
commissioner's sole discretion.
h.
Any entity providing funds to the SMH program will be permitted to establish
additional rules and guidelines under which those funds may be used, as long as
they do not violate state or federal law.
i. Grant amounts are limited to $10,000.00
per home.
2. Application
Process.
a. Homeowner creates an online
profile and completes the application.
b. Homeowner submits application to
SMH.
c. The SMH staff and/or its
TPA will review all applications for completeness and will perform appropriate
audits to verify the accuracy of the information on the application and that
the applicant meets all eligibility rules. Verified applicants are placed in
the order received. Grants are awarded through a lottery process, subject to
the availability of funds.
d. When
an application is approved, an approval letter is sent to the
applicant.
e. Once notified that
application is approved, Homeowner will then provide required documentation for
eligibility: evidence of homestead exemption; a copy of the declaration page of
homeowner insurance policy and copy of declaration page of flood insurance
policy if the home is in a Special Flood Hazard Area.
f. Homeowner shall select a Certified IBHS
Evaluator from a list of evaluators provided by SMH,
www.mid.ms.gov or IBHS,
www.fortifiedproviders.com.
g. Evaluator pre-qualifies the home to
determine whether the home can be FORTIFIED and, if so, identifies all
improvements required to achieve IBHS FORTIFED Roof or an IBHS successor
designation and reports findings to SMH or its TPA. The Evaluator's fee is paid
by the homeowner.
3.
Authorization to Begin Work
a. Homeowner will
select three (3) Contractors from the approved list of Contractors (Contractors
found at SMH www.mid.ms.gov or IBHS,
www.fortifiedproviders.com.
b. Homeowner provides Evaluator's report to
Contractors and obtains Contractor bids necessary to perform work to achieve
FORTIFIED roof designation as outlined in Evaluator's report.
c. Contractor bids are forwarded to SMH Staff
and/or the TPA for review.
d. The
applicant then selects a Contractor of its choice from bids received and enters
into an agreement with the Contractor to perform the FORTIFIED work.
Contractors are not authorized to begin work until SMH or its TPA has
approved.
e. The Evaluator will
conduct all required evaluations, including the required interim inspection
during construction and the final inspection.
f. Once the FORTIFIED work is completed, the
Contractor submits a copy of the signed contract to SMH, along with supporting
documentation to Evaluator as evidence of work completed to achieve FORTIFEID
designation, an invoice seeking payment, and an affidavit stating the FORTIFIED
standard was met by their work.
g.
Evaluator sends supporting documentation to SMH or its TPA confirming that the
work has been completed according to the FORTIFIED specifications.
4. Payment of Grant.
a. Release of Funds. Grant funds will be
released on behalf of an approved applicant once an IBHS FORTIFIED certificate
has been issued for the home. The funds will be paid by SMH or another
designated entity, on behalf of the homeowner, directly to the Contractor that
performed the FORTIFIED work.
b.
SMH or its designated entity pays the Contractor costs covered by the grant;
the homeowner pays the remaining cost, if any, to the Contractor after
receiving an IBHS FORTIFIED Certificate.
c. SMH may conduct random re-inspections to
detect any fraud and submit any irregularities to the MID Investigations and
Consumer Protection Division.