19 Miss. Code. R. 5-7.08 - Contractor Conflict of Interest
1. Contractors may
not have a financial interest in any project for which they perform work toward
a FORTIFIED designation other than for payment on behalf of the homeowner by
the SMH program for work performed.
2. Contractors cannot be the Evaluator for a
FORTIFIED designation on any project funded by the SMH program.
3. It is the Contractor's responsibility to
report to the SMH program any potential conflicts of interest before work
commences on any job funded by the program.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.