19 Miss. Code. R. 8-1.15 - Permits
(1) An application for a permit shall be
filed with the department in accordance with this Regulation for all elevator
work covered under these rules.
(2)
Each application for a permit shall be accompanied by copies of specifications
and accurately-scaled and fully-dimensioned plans that clearly indicate
location of the elevator in the building; the location of the machinery room
and the equipment to be installed, relocated or altered; all structural
supporting members, including foundations; and a specification of all materials
to be used and all loads to be supported or conveyed. The plans and
specifications shall be sufficiently complete to illustrate all details of
construction and design.
(3) The
applicable fees shall accompany each permit application.
(4) A permit may be revoked for any of the
following reasons:
(a) Where any false
statements or misrepresentations were made as to the material facts in the
application, plans, or specifications on which the permit was based.
(b) Where the permit was issued in error and
should not have been issued in accordance with this chapter.
(c) Where the work detailed under the permit
is not being performed in accordance with the provisions of the application,
plans, or specifications or with this chapter or conditions of the
permit.
(d) Where the elevator
contractor to whom the permit was issued fails or refuses to comply with a STOP
WORK order.
(5) A permit
expires if the work authorized by a permit is not commenced within twelve (12)
months after the after the date of issuance.
(6) A permit is not required for a
repair.
(7) The Administrator may
allow an extension of time at his or her discretion.
Notes