2 Miss. Code. R. 903-5.1 - Approved Practices
Approved Practices.
A. Erosion Control
| Practice Number | Practice Name | Cost Share Rate |
| SEC-1 | Terraces | 60% |
| SEC-2 | Field Borders | 60% |
| SEC-3 | Grassed Waterways | 60% |
| SEC-4 | Conservation Tillage (No-Till) | 60% |
| SEC-5 | Water & Sediment Control Basins | 60% |
| SEC-6 | Establishment of Permanent Vegetation | 60% |
| SEC-7 | Critical Area Planting | 60% |
| SEC-8 | Tree Planting | 60% |
| SEC-9 | Grade Stabilization Structure | 60% |
| SEC-10 | Strip Cropping Systems | 60% |
| SEC-11 | Reduced Tillage | 60% |
| SEC-12 | Cover & Green Manure Crop | 60% |
| SEC-13 | Pasture & Hayland Planting | 60% |
| SEC-14 | Streambank & Shoreline Protection | 60% |
| SEC-15 | Chiseling and Subsoiling | 60% |
| SEC-16 | Heavy use Area Protection | 60% |
| SEC-17 | Forest Land Erosion Control System | 60% |
| SEC-18 | Prescribed Grazing | 60% |
| SEC-19 | Nutrient Management | 60% |
| B. Water Conservation | ||
| WC-1 | Irrigation Land Leveling | 60% |
| WC-2 | Irrigation System, Tailwater Recovery | 60% |
| WC-3 | Irrigation Water Conveyance Pipe Line | 60% |
| WC-4 | Irrigation Storage Reservoirs | 60% |
| WC-5 | Establishment of Permanent Vegetation | 60% |
| WC-6 | Tree Planting | 60% |
| WC-7 | Ponds | 60% |
| WC-8 | Animal Waste Control Facilities | 60% |
| WC-9 | Diversions | 60% |
| WC-10 | Livestock Pond Renovation | 75% |
| C. Wildlife | ||
| W-1 | Field Borders | 60% |
| W-2 | Filter Strip | 60% |
| W-3 | Prescribed Burning | 60% |
| W-4 | Wildlife Upland Habitat Management | 60% |
| W-5 | Wildlife Wetland Habitat Management | 60% |
| D. Water Quality | ||
| WQ-1 | Integrated Crop Management | 60% |
| WQ-2 | Fencing | 60% |
| WQ-3 | Trough or Tank | 60% |
| WQ-4 | Agrichemical Mixing Center | 60% |
| WQ-5 | Structure for Water Control | 60% |
| WQ-6 | Buffer Zone | 60% |
| WQ-7 | Check Dam | 60% |
| WQ-8 | Concrete Grid & Modular Pavement | 60% |
| WQ-9 | Constructed Wetland | 60% |
| WQ-10 | Detention Basin | 60% |
| WQ-11 | Lined Waterway | 60% |
| WQ-12 | Parking Lot Storage | 60% |
| WQ-13 | Paved Flume | 60% |
| WQ-14 | Rock Outlet Protection | 60% |
| WQ-15 | Slope Drain | 60% |
| WQ-16 | Sub Surface Drain | 60% |
| WQ-17 | Water Bar | 60% |
| WQ-18 | Retention Basin | 60% |
| WQ-19 | Silt Fence | 60% |
| WQ-20 | Permanent Seeding | 60% |
| WQ-21 | Stream Crossing | 60% |
| WQ-22 | Chemical Container/Used oils-Lubricants Recycling | 0 |
| WQ-23 | Cattle Feed & Waste Management Facility | 60% |
| WQ-24 | Well Decommissioning | 60% |