30 Miss. Code. R. 901-21.2
Attesting to Quality and Responsibility for Surveys
To provide the client with the assurance that the work was performed under the direct supervision of a licensee, and was performed to a certain standard, documentation shall be sealed and signed by the licensee in responsible charge, including, but not limited to, the following:
1. When a boundary, route, easement, or lease
survey is performed, a plat shall be prepared and the plat shall bear the seal
and signature of the Professional Surveyor in responsible charge.
2. When a topographic survey, hydrographic
survey or construction survey is performed at the request of a client, any
plat, map or report that is the final product of that licensee for that project
shall be sealed and signed by the Professional Surveyor or the Professional
Engineer in responsible charge. If a topographic survey, hydrographic survey or
construction survey is performed by a licensee to obtain data to be used by
that licensee to perform calculations or to be incorporated into a final
product of that project, then the final product of that project shall be sealed
and signed by the Professional Surveyor or the Professional Engineer in
responsible charge.