33 Miss. Code. R. 2-3.7.7 - Construction Phase Submittals, Approvals, and Actions
The following submittals, approvals, and actions will be required during the construction phase of the project. The Department may establish other time frames within the loan agreement when properly justified.
1. Within 90 days after approval of
plans, specifications and contract documents by the Department (1) all
construction related contracts must be advertised for bids and proof of such
advertisement must be submitted, (2) all local funds necessary for the project
must be secured, and proof of such local funds must be submitted, and (3) clear
site certificates from the loan recipient and title counsel for all real
property must be submitted.
2.
Within 120 days after approval of plans, specifications and contract documents
by the Department, the loan recipient must open bids on all construction
related contracts.
3. Within 14
days after receipt of bids, the loan recipient must submit all DBE, EEO, and
related documents.
4. Within 21
days after receipt of bids for new construction, the loan recipient must submit
all bid packages.
5. Within 60 days
after receipt of bids, the loan recipient must execute all construction
contract documents, must submit a copy of all executed contract documents, and
must issue and submit a copy of the notice to proceed on all such
contracts.
6. By the date initially
established in the loan agreement (which is based upon approximately 50% of
contract time) the loan recipient must submit (1) a completed operation and
maintenance manual for all drinking water treatment facilities to be
constructed in whole or in part with DWSIRLF funds and (2) a plan on how the
loan recipient will insure that operators are hired and certified in accordance
with state law by the date in (g) below.
7. By the date initially established in the
loan agreement (which is based upon approximately 90% of contract time) the
loan recipient must (1) enact the approved user charge system and
ordinance/corporate resolution and submit proof of such enactment, (2) if
applicable, secure approval of the operation and maintenance manual, (3) hire
all operators, and (4) submit their names and submit the operator certification
numbers for the operators certified in accordance with state law.
8. Within 10 days after construction
completion of each construction contract, the loan recipient must notify the
Department of construction completion.
9. The Department will perform a final
construction observation within 30 days after the current construction contract
completion date, unless further delayed by the Department pursuant to review of
the loan recipient's request and justification for such delay. Should the
Department decide that the construction completion is being unreasonably
delayed, a final construction observation may be immediately performed by the
Department. The final construction observation by the Department is only for
the purpose of determining final loan allowable costs.
10. Within 30 days after the current
construction contract completion date, all change orders which include time
extensions exceeding 30 days beyond the original contract completion date,
and/or documentation showing the loan recipient is implementing all legal
remedies provided in the contract documents for failure to complete
construction when required, must be submitted to the Department for an
allowability determination.
11.
Within 30 days after the final construction observation performed by the
Department, the loan recipient must submit: final payment request; approvable
summary change orders for all construction contracts; full scale record
drawings with all revisions shown and noted for the entire project funded in
whole or in part with DWSIRLF funds; the registered engineer's certification of
compliance with plans, specifications, and contract documents; appropriate
bacteriological test results; final construction phase professional services
contract amendments, if any; and all other administrative forms and documents
required by the loan agreement. Loan payment requests submitted after
this date are not allowable, regardless of when the costs were
incurred.
12. Any other
submittals or actions required by the loan agreement must be performed when so
required and are subject to review and approval by the
Department.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.