"Commissioning Tests" means the tests applied to a DGF by an Interconnection Customer after construction is completed to verify that the DGF does not create Adverse System Impacts. At a minimum, the scope of the Commissioning Tests performed shall include the commissioning test specified by IEEE Standard 1547 section 5.4 "Commissioning Tests."