The EU shall use the Level 2 Interconnection Review procedure to evaluate an Interconnection Request when:

1. The DGF has a Nameplate Capacity rating of 2 MW or less;
2. The Interconnection Equipment proposed for the DGF is Certified; and
3. The aggregated total of the Nameplate Capacity of all of the generators on the circuit, including the proposed DGF, is 2 MW or less.

Notes

39 Miss. Code. R. 4-I-6-100
Adopted 1/3/2016 Amended 8/12/2022 Amended 11/6/2022