39 Miss. Code. R. 4-I-6-100
The EU shall use the Level 2 Interconnection Review procedure to evaluate an Interconnection Request when:
1. The DGF has a Nameplate Capacity rating of
2 MW or less;
2. The
Interconnection Equipment proposed for the DGF is Certified; and
3. The aggregated total of the Nameplate
Capacity of all of the generators on the circuit, including the proposed DGF,
is 2 MW or less.