39 Miss. Code. R. 4-I-6-103
The Level 2 Interconnection Review shall then be conducted in accordance with the following procedures:
1. An EU shall, within 10 business days after
receipt of the Interconnection Request, inform the Interconnection Customer in
writing or by electronic mail that the Interconnection Request is complete or
incomplete and indicate what, if any, materials are missing. As part of this
process, the EU shall assign a Queue Position. The Queue Position of the
Interconnection Request shall be used to determine the potential Adverse System
Impact of the DGF based on the relevant screening criteria. If there are higher
queued Interconnection Requests on the same radial line circuit, the EU shall
evaluate the Interconnection Requests by performing any Level 2 screens
requiring aggregate capacity calculations and determine if the DGF in
combination with the higher queued Interconnection Requests exceeds any of the
aggregate capacity requirements. If an aggregate capacity requirement is
exceeded, the EU shall notify the Interconnection Customer and shall not be
obligated to meet the timeline for reviewing the Interconnection Request until
such time as the EU has completed the review of all other Interconnection
Requests that have a higher Queue Position and impact the aggregate capacity
calculation that has been exceeded.
2. At the time an EU determines additional
information is required to complete an evaluation, the EU shall request the
information. The time necessary to complete the evaluation may be extended by
mutual agreement of the parties, but only to the extent of the time required
for receipt of the additional information. During an extension of time to
submit additional information, the EU may not alter the Interconnection
Customer's Queue Position.
3.
Within 20 business days after the EU notifies the Interconnection Customer that
it has received a completed Interconnection Request, the EU shall:
a. Evaluate the Interconnection Request using
the Level 2 screening criteria;
b.
Review any analysis provided by the Interconnection Customer, using the same
criteria used by the customer; and
c. Provide the Interconnection Customer with
the EU's evaluation, including a comparison of the results of its own analyses
with those of Interconnection Customer, if applicable. When an EU does not have
a record of receipt of the Interconnection Request and the Interconnection
Customer can demonstrate that the original Interconnection Request was
delivered, the EU shall expedite its review to complete the evaluation of the
Interconnection Request within 20 business days of the Interconnection
Customer's re-submittal.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.