39 Miss. Code. R. 4-II-2-106 - "Distributed Generation Interconnection Customer" or "DGIC"

"Distributed Generation Interconnection Customer" or "DGIC" is any electricity customer, such as an industrial, large commercial, residential or small commercial customer, that generates electricity on the customer's side of the meter using a Renewable Energy source. The electricity customer must own or lease the DGF producing the Renewable Energy on the electricity customer's side of the meter in order to qualify as a DGIC under this MDGR, unless otherwise approved by the Commission.

Notes

39 Miss. Code. R. 4-II-2-106
Adopted 1/3/2016 Amended 8/12/2022 Amended 11/6/2022

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.