4 Miss. Code. R. 3-1.5 - Completed Project Analysis
(a)
As
provided in the Memoranda of Understanding: Final project analysis
will include elements defined and described in the MOU for each project, where
available.
(b)
Recommendations in Addition to the Presented Activities of the
Memoranda of Understanding:
(1)
Upon the original date of stated completion, visit project site in order to
perform the following for:
(i) Tangible
Project Components:
(A) Document that the
project is constructively complete in accordance with the terms of the
agreement, Memoranda of Understanding and the engineering specifications of the
project.
(B) Document that the
related infrastructure required to support the operations of the project is
operational as defined by the terms of the agreement, if applicable.
(ii) Intangible Project
Components:
(A) Document that the full amount
of capital investment has been received as required by the completion date of
the project from the project company.
(B) Document that the number of jobs created
by the completion date of the project is equal to or greater than the amount
agreed upon in the MOU related to the employment aspect of the
project.
(C) Document that the
project has the capacity and ability to produce the intended benefit within the
timeframe specified by the MOU.