6 Miss. Code. R. 9-1.18 - Project Reimbursement and Completion Requirements
All projects receiving a grant must adhere to the following rules before requests for payment can be processed and payment can be made:
A. The applicant must have a
current W-9 form with a Federal Tax ID Number on file at MDA and must register
as a vendor in the State of Mississippi's MAGIC system and in
Paymode.
B. The applicant must list
the project name (as listed on the grant application form) and the grant fund
number (as listed in the grant agreement) in all correspondence regarding an
approved project.
C. A copy of
vendor invoices and a copy of proof of payment to vendors must be provided with
all invoices submitted to MDA, along with request for payment form. (Examples
of proof of payment include: canceled checks, bank statements, vendor receipts,
etc.)
D. The applicant must return
a complete, final report to MDA's Financial Resources Division no later than 60
days from the project completion date.
E. Funding for Ready Site
grants will not be disbursed until a final report is submitted, accepted, and
approved by MDA.
F. Funding for
Premier Site grants will be made available on a reimbursement
basis on a drawdown schedule agreed upon by MDA. The final 10% of
Premier Site grant funds will be disbursed after a final
report is submitted, accepted, and approved by MDA.
G. MDA may conduct a final site inspection
prior to final grant closeout.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.