458 Neb. Admin. Code, ch. 9, § 001

The owner of a dam shall provide written notice to the Department at least ten days before construction, reconstruction, enlargement, alteration, breach, removal, or abandonment of the dam is to begin. Notice shall be given immediately after foundation preparation and principal spillway construction and at least two days prior to backfilling the spillway. Notices must be in writing and addressed to the Chief Engineer or the Construction Inspector of the Department's Dam Safety Section. Notices may be delivered to the Department by mail, facsimile or electronic mail.