Nev. Admin. Code § 319.979 - Submission of progress report by project sponsor

Each project sponsor shall submit a progress report to the Division every 90 days beginning on the date he or she is notified by the Division of a reservation of tax credits. The failure of a project sponsor to submit a progress report within that period may result in the forfeiture of the reservation of tax credits for the project.

Notes

Nev. Admin. Code § 319.979
Added to NAC by Housing Div. by R057-97, eff. 1-15-98

NRS 319.140, 319.145

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.