Nev. Admin. Code § 445B.298 - Application: Official date of submittal
Except as otherwise provided in NAC 445B.3364, 445B.3395, 445B.3457 or 445B.3683, the official date of submittal of an application for:
1. An operating permit;
2. An operating permit to construct;
3. A revision of an existing operating permit; or
4. A revision of an existing operating permit to construct,
is the date on which the Director determines that the application is complete.