Nev. Admin. Code § 624.693 - Informational form regarding mechanics' and materialmen's liens
The informational form that a general building contractor is required to provide regarding mechanics' and materialmen's liens pursuant to paragraph (b) of subsection 3 of NRS 624.600 to the owner of a single-family residence with whom he or she has contracted must be as follows:
'NOTICE TO OWNER'
Pursuant to NRS 108.221 to 108.246, inclusive, a contractor, subcontractor, laborer, supplier of materials or other person or entity who:
This means that after a court hearing, your property could be sold by an officer of the court and the proceeds of the sale used to satisfy the amount you owe. If you did not ask for and receive releases of liens from the contractors' subcontractors, laborers or suppliers of materials, a lien may be placed on your property or you may be sued even if you have paid your contractor in full.
To preserve their right to file a claim or lien against your property, certain claimants, such as subcontractors, laborers and suppliers of materials, are each required to provide you with a document called a "preliminary or pre-lien notice." A preliminary or pre-lien notice is not a lien against your property. Its purpose is to notify you regarding persons or entities who may have a right to file a lien or claim against your property if they are not paid. To perfect their lien rights, contractors, subcontractors, laborers and suppliers of materials must file mechanics' liens with the county recorder, which then become recorded liens against your property. Generally, the maximum time allowed for filing a mechanics' lien against your property is 90 days after substantial completion of your project.
TO ENSURE EXTRA PROTECTION FOR YOURSELF AND YOUR PROPERTY, YOU MAY WISH TO TAKE ONE OR MORE OF THE FOLLOWING STEPS:
* Some stationery stores sell waiver and release forms if your contractor does not have them. The subcontractors, laborers and suppliers of materials from whom you obtain releases should be those persons or entities who have filed preliminary or pre-lien notices with you. If you are not certain which subcontractors, laborers and suppliers of materials are working on your project, you may obtain a list from your contractor. In regard to projects involving improvements to a single-family residence or a duplex owned by an individual, the persons signing these releases lose their right to file a mechanics' lien against your property. In regard to other types of projects, obtaining such releases may still be important, but may not provide complete protection.
* To protect yourself by use of a waiver and release form, you must be certain that all subcontractors, laborers and suppliers of materials who work on your project sign a waiver and release form. If a mechanics' lien has already been filed against your property, in most cases the lien can only be released voluntarily by a recorded "release of mechanics' lien," which is signed by the person or entity that filed the mechanics' lien against your property. However, if the person or entity that filed the lien fails to bring an action to enforce the lien in a timely manner, the lien may be removed without voluntary action on the part of that person or entity. You should not make final payment on your project until all mechanics' liens that are filed against your property have been removed.
TO PROTECT YOURSELF FULLY, YOU SHOULD CONSULT AN ATTORNEY:
Notes
NRS 624.100, 624.600