Nev. Admin. Code § 704.195 - Monthly reports
1. Not later than
45 days after the end of each month in every deferred energy period, each
electric utility and gas utility shall submit to the Commission a report
containing all transactions and calculations affecting the deferred energy
accounts. The monthly reports must include any other information or data
required by the Commission to expedite or facilitate the deferred energy
application or annual rate adjustment application and hearing necessary to
clear the balances of deferred energy accounts.
2. Each electric utility shall submit in its
monthly reports for electric operations the monthly cost of all energy
generated and purchased, indicating:
(a) The
number of megawatt-hours generated as to quantity, cost and type of fuel used
in each generating unit;
(b) The
number of megawatt-hours purchased and the cost, including demand charges, for
each supplier by rate schedule or contract;
(c) The number of megawatt-hours delivered by
a renewable energy facility owned by the electric utility and the cost charged
based on a just and reasonable price established by the Commission pursuant to
NRS
704.752; and
(d) The basis of charges and data supporting
those charges.
3. Each
gas utility shall submit in its monthly reports for gas operations the monthly
cost of all gas purchased, indicating:
(a) The
quantity and cost of gas purchased from each supplier by rate schedule or
contract; and
(b) The basis of the
charges and the invoices supporting the charges.