N.H. Admin. Code § Ed 321.15 - School Building Aid Application Information
The following information shall be included when submitting a building aid application:
(a)
General project information including:
(1)
Project location;
(2) Contact
person;
(3) Estimated cost of the
project;
(4) Grade span;
and
(5) Brief description of the
project;
(b)
Identification of architect and the owner's project manager (OPM), if required
by RSA
198:15-c;
(c) Identification of the total number of
students, full-time staff, student drivers, and the anticipated number of
parking spaces after project completion;
(e) A needs assessment of the existing
building in accordance with
Ed
321.12;
(g) If seeking ranking points for school
security per Ed
321.16(f)(2), a copy of a school
security assessment not more than 3 years old, completed by the New Hampshire
homeland security and emergency management;
(h) A completed "Condition Evaluation Form,"
May 2024;
(i) The net energy use
intensity (EUI) of the existing facility over the past 5 years and the
estimated EUI of the proposed facility 5 years following completion of
construction;
(j) A summary of the
district's commitment to good maintenance including, but not limited to:
(1) A description of the capital reserves
program;
(2) The history of the
district's annual budget for the past 5 years, to support good maintenance;
and
(3) A description of how the
district budgets for preventative maintenance and long-term capital
improvements;
(k) The
design capacity and the calculations and data used to determine the design
capacity in accordance with
Ed
321.08;
(l) Square footage of the building before and
after construction;
(m) Budget and
financial information, including but not limited to the following:
(1) Estimated project budget and unit
costs;
(2) Anticipated funding
sources and anticipated amounts from each source;
(3) Amount of district debt;
(4) Total assessed valuation; and
(5) Percent debt to
valuation;
(n) A
statement of assurance, signed by the chair of the school board, which
indicates the following:
(1) Maintenance and
service for all installed equipment at the school facility shall be according
to the manufacturer's instructions;
(2) Property insurance to pay for damages
resulting from weather and other natural events shall be maintained;
(3) Ongoing operations and maintenance shall
be provided in accordance with Ed 321.30;
(4) Plans shall be submitted to the state
fire marshal's office for a plan review prior to construction;
(5) Energy efficiency reimbursement
applications shall be submitted to the school district 's regulated utility
provider; and
(6) A request for
project review shall be submitted to the department of cultural resources,
division of historical resource, prior to construction;
(o) School board meeting minutes approving
the project, which clearly identify the following:
(1) The project as described in the building
aid application;
(2) The total
project costs listed in the building aid application; and
(3) A statement that the project shall be put
forth for voter consideration subject to receiving building
aid;
(p) An aerial view
of the existing building(s) with the total square footage and the year of
construction labeled for the original building and any additions;
(q) Site plan which indicates the boundaries
of school-owned property to be developed, the location of proposed
construction, location of wetlands and bodies of water, and location of
existing structures;
(r)
Preliminary design plans that have the following:
(1) Labels for the proposed use of each
space;
(2) Labels for the square
footage of each space, excluding spaces less than 100 square feet;
(3) The total square footage of each level;
and
(4) The overall exterior
building dimensions;
(s)
A plan with each space color coded by the primary use as follows:
(1) General studies, shaded green;
(2) Specialized educational spaces such as
world language, art, and music, shaded blue;
(3) Special education areas such as speech
and language pathology rooms, occupational therapy and physical therapy rooms,
and case manager rooms, shaded purple;
(4) Core spaces such as library and media
center, kitchen, cafeteria, and gymnasium spaces, shaded yellow;
(5) Administrative areas such as reception
areas, vestibule areas, copy and storage rooms, nurse's office, guidance
offices, social worker offices, staff rooms, and conference rooms, shaded
orange; and
(6) Building services
and miscellaneous areas such as bathrooms, server rooms, custodial closets,
mechanical rooms, corridors, and stairs, shaded gray;
(t) A summary table of the total square
footage for each of the color-coded categories listed in (s) above;
(u) If the project includes a new site
location, site information including but not limited to:
(1) The total usable area;
(2) Descriptions of the restrictions the site
might have;
(3) The status of any
necessary testing and permitting;
(4) The proposed grading plan; and
(5) A copy of the appraisal conducted as part
of the land acquisition; and
(v) A digital copy of the
application.
Notes
#8265, eff 1-22-05; ss by #10363, eff 6-15-13
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
(a) For purposes of calculating school building aid , total eligible costs include:
(1) The costs for acquisition of land and site development ;
(2) Construction costs;
(3) Planning and design costs, including:
a. Architectural fees;
b. Engineering fees; and
c. Project manager fees if required by RSA 198:15-cIV;
(4) Purchase of furniture, fixtures, and equipment necessary for the completion of a building, including commissioning fees, computers and software necessary to operate the security, HVAC, or other building system components, fire retardant window treatments, seating, lockers, clock systems, sound systems, and other equipment that is integral to the building and educational services; and
(5) Purchase or lease-purchase of mechanical, structural, or electrical equipment, including the cost of installation of such equipment, which is designed to improve energy efficiency or indoor air quality in buildings.
(b) Costs related to financing such as bonding charges and interest shall not be included in the total cost of school building construction and shall not be eligible for inclusion in the calculation of school building aid .
(c) Costs for construction work that is not located on school property shall not be eligible for inclusion in the calculation of school building aid . This shall include, but not be limited to, costs for construction of municipally owned sidewalks, costs for improvements to municipally owned roadways, costs for installation of traffic control devices, and costs to construct or improve utility plant to bring service to the school.
Notes
#8265, eff 1-22-05; ss by #10363, eff 6-15-13