N.J. Admin. Code § 14:8-5.9 - Interconnection reporting requirements for EDCs
(a) Each EDC
with one or more customer-generators connected to its distribution system shall
submit two interconnection reports per year, one covering January 1 through
June 30 and one covering July 1 through December 31. The EDC shall submit the
reports by August 1 and February 1, respectively.
(b) The EDC shall submit the reports required
by this section electronically, in PDF format, to oce@bpu.state.nj.us. In
addition, the EDC may, at its discretion, submit a paper copy of the reports by
hand delivery or regular mail to the Secretary, Board of Public Utilities, 44
South Clinton Avenue, 9th Floor, PO Box 350, Trenton, New Jersey 08625-0350.
The EDC may, at its discretion, submit the interconnection report together with
the net metering report required under
14:8-4.5.
(c) Each report shall contain the following
information regarding customer-generator facilities that interconnected with
the EDC's distribution system for the first time during the reporting period,
listed by type of renewable energy technology:
1. The number of customer-generators that
interconnected;
2. The estimated
total rated generating capacity of all customer-generator facilities that
interconnected; and
3. The total
cumulative number of customer-generators that interconnected between June 15,
2001 and the end of the reporting period, including the customer-generators in
(c)1 above.
(d) The
information required under (c) above shall be listed by type of class I
renewable energy, as set forth at
14:8-2.5(b), as
follows:
1. Solar PV technology;
2. Wind technology;
3. Biomass; or
4. A renewable energy technology not listed
at (d)1 through 3 above. In such a case, the report shall include a description
of the renewable energy technology.
Notes
See: 41 N.J.R. 2215(a), 42 N.J.R. 78(a).
Former N.J.A.C. 14:8-5.9, Enforcement, recodified to N.J.A.C. 14:8-7.9.
Administrative change.
See: 43 N.J.R. 1896(a).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.