N.J. Admin. Code § 16:47-9.4 - Pre-application process
(a) A
pre-application meeting is intended to provide a lot or site owner with
guidance on the access application process, familiarize the Department with the
proposed development, and identify potential issues that should be addressed in
the access application. Guidance provided at this meeting shall not be deemed
to constitute final Department approval.
(b) A pre-application meeting is mandatory
when applying for a major with planning review permit, a permit for a new
street, and when a new traffic signal is proposed. A pre-application meeting is
not required when applying for a major permit, but may be held if requested.
Meetings are not normally necessary when applying for a minor permit.
(c) All pre-application meetings require the
following:
1. A pre-application meeting
request shall be made in writing to the Bureau of Major Access Permits at the
address found at
N.J.A.C.
16:47-9.5(g).
2. Copies of the information specified in the
Pre-Application Meeting Checklist found in N.J.A.C. 16:47 Appendix H-1 shall be
submitted with the request for a pre-application meeting.
3. The Bureau of Major Access Permits will
arrange the pre-application meeting with the lot or site owner or his or her
representative, who shall be accompanied by the professional who will be
preparing the access application. The lot or site owner shall notify the
municipal and county engineers of the scheduled meeting at least seven days in
advance of the meeting and include, with the notification, copies of all
materials submitted to the Department. Copies of these notifications shall be
submitted to the Department at the pre-application meeting. Attendees applying
for a major with planning review permit should be prepared to discuss the study
area and study locations to be analyzed in the required traffic impact
study.
(d) Applications
shall be submitted within 12 months of the date of the meeting. If an
application is not received within this timeframe, another pre-application
meeting will be held pursuant to this section prior to the submission of an
application.
(e) Lot or site owners
may request review of the proposed study area and study locations to be
analyzed in a traffic impact study prior to requesting a pre-application
meeting. Review may also be requested after a pre-application meeting, but
prior to submitting an access application. The request for the review shall be
accompanied by a fee in the amount of $ 1,000, which shall be credited toward
the application fee, and the information required to delineate the traffic
impact study area and study locations as found in N.J.A.C. 16:47 Appendix
F-1.4, Scope of Study. Within 30 days of the submission of this information and
fee, the Department will either provide comments or concur with the proposed
study area and study locations to be analyzed in the traffic impact study. If
the request for review of the study area is made prior to the pre-application
meeting, the pre-application meeting will not be held until the Department
review is complete.