N.J. Admin. Code § 7:13-7.9 - Permit-by-rule 9 - general construction activities in a tidal flood hazard area
(a) Permit-by-rule
9 authorizes general construction activities in a tidal flood hazard area,
provided the conditions at
N.J.A.C.
7:13-6.7 are met and:
1. The existing ground elevation is not
raised in any floodway;
2. No
aboveground structure is constructed in any floodway;
3. No habitable building, fuel tank, solar
panel, or underground utility line that conveys a gas or liquid is
constructed;
4. No disturbance is
located within 25 feet of any top of bank, unless the project lies adjacent to
a lawfully existing bulkhead, retaining wall, or revetment along a tidal water
or impounded fluvial water;
5. Any
clearing, cutting, and/or removal of riparian zone vegetation is limited to
actively disturbed areas; and
6.
The project, in combination with all activities onsite since November 5, 2007,
will not result in a net loss of greater than one-quarter acre of riparian zone
vegetation.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.