N.M. Admin. Code § 1.12.5.11 - REPORTING REQUIREMENTS
A. Project
status reports. For all projects that require office oversight, the lead agency
project manager shall submit an agency approved project status report on a
monthly basis to the office.
B.
Independent verification and validation assessment reporting. The office
requires all projects subject to oversight to engage an independent
verification and validation contractor unless waived by the office. The
IV&V contractor shall perform the following activities.
(1) Prepare an initial risk assessment report
at project inception. This assessment will include recommended mitigation
activity to reduce the impact and probability of the identified risk.
(2) Prepare initial status report at project
inception to disclose the effectiveness of project management and whether the
documented project activities are meeting the objectives set forth by
project.
(3) Prepare interim
reports based on the phases as indicated within the project schedule. Included
in the report will be an evaluation on whether product development requirements
are being met, project management is effective, continuing risk analysis, and
how the project is implementing previous recommended risk mitigation
strategies.
(4) Prepare a post
implementation assessment at project close to indicate whether project
objectives were met based on the project's scope and acceptance
criteria.
(5) Submit each risk
assessment report, status report, interim report, and post-implementation
assessment report to the office within five (5) business days of each
deliverable due date as indicated on the project schedule. All reports must be
submitted to the agency heads and the office.