N.M. Admin. Code § 17.7.3.11 - ACTION PLAN
A. The
utility's action plan shall:
(1) detail the
specific actions the utility shall take to implement the IRP spanning a three
year period following the filing of the utility's IRP;
(2) detail the specific actions the utility
shall take to develop any resource solicitations or contracting activities to
fulfill the statement of need as accepted by the commission; and
(3) include a status report of the specific
actions contained in the previous action plan.
B. The utility shall update the commission by
filing two reports describing the utility's implementation of the action plan.
These reports shall be filed in the existing IRP docket one year after the
filing of the IRP, and two years after the filing of the IRP,
respectively.
C. An action plan
does not replace or supplant any requirements for applications for approval of
resource additions set forth in New Mexico law or commission
regulations.
D. The utility shall
promptly notify the commission and participants of material events that would
have the effect of changing the results of the utility's action plan had those
events been recognized when the action plan was developed.
E. In accepting the action plan, the
commission shall take into consideration contractual obligations as between the
utility and any regional transmission organizations or balancing authorities of
which the utility is a member.