N.M. Admin. Code § 17.9.569.2 - SCOPE

A. This rule applies to every electric utility including rural electric cooperatives and investor-owned utilities operating within the state of New Mexico that is subject to the jurisdiction of the New Mexico public regulation commission. These standards and procedures apply to both qualifying and non-qualifying facilities.
B. The standards and procedures described in this rule 17.9.569 NMAC apply only to the interconnection of generating facilities with a rated capacity greater than 10 MW. The standards and procedures described in 17.9.568 NMAC apply to the interconnection of generating facilities with a rated capacity up to and including 10 MW.