N.M. Admin. Code § 17.9.589.9 - Specific Reliability Metrics Reporting Requirements
A. MAIFI is not required to be reported
unless the utility has installed the necessary technology and has usage data
for at least six months across eighty percent of its electric system.
B. Activities that occur on MEDs should be
separately analyzed and reported.
C. A utility that provides electric service
in more than one state may:
(1) identify major
events based on the reliability events experienced by the combined service
territories; and
(2) illustrate the
effect of identifying major events based on reliability events experienced only
in the New Mexico service territory.
D. A utility may categorize interruptions
into more detailed interruption cause categories that are subsets of the
defined interruption cause code categories. The utility shall:
(1) list sub-causes when weather is the
primary interruption cause code;
(2) list sub-equipment components when using
the equipment interruption cause code;
(3) include planned interruptions;
and
(4) include the utility's
methodology of how it classifies interruptions.