N.M. Admin. Code § 19.15.17.9 - PERMIT APPLICATION AND REGISTRATION
A. An operator shall use the appropriate form
C-144 to apply to the division for a permit to construct or use a pit or
proposed alternative method, or to register a below-grade tank. The operator
shall submit the form C-144 either separately or as an attachment to a permit
application for a facility with which the pit, below-grade tank or proposed
alternative method will be associated. An operator shall use a C-101, C-103 or
applicable bureau of land management form to notify the appropriate division
district office of construction or use of a closed-loop system.
B. The permit application shall include a
detailed plan as follows.
(1) Permanent pits.
A registered professional engineer shall certify engineering, design and
construction specifications as contained in the plan for permanent pits. The
plan shall include:
(a) a quality
control/quality assurance construction and installation plan;
(b) operating and maintenance
procedures;
(c) a closure
plan;
(d) a hydrogeologic report
that provides sufficient information and detail on the site's topography,
soils, geology, surface hydrology and ground water hydrology to enable the
division's Santa Fe office to evaluate the actual and potential effects on
soils, surface water and ground water;
(e) detailed information on dike protection
and structural integrity; and leak detection, including an adequate fluid
collection and removal system;
(f)
liner specifications and compatibility;
(g) freeboard and overtopping
prevention;
(h) prevention of
nuisance or hazardous odors, including H2S;
(i) an emergency response plan, unless the
permanent pit is part of a facility that has an integrated contingency
plan;
(j) type of oil field waste
stream;
(k) climatological factors,
including freeze-thaw cycles;
(l) a
monitoring and inspection plan;
(m)
erosion control; and
(n) other
pertinent information the environmental bureau in the division's Santa Fe
office requests.
(2)
Temporary pits. The plan for design and construction of a temporary pit shall
follow applicable liner manufacturers' requirements. The permit application
also shall include operating and maintenance procedures, a closure plan and
hydrogeologic data that provides sufficient information and detail on the
site's topography, soils, geology, surface hydrology and ground water hydrology
to enable the appropriate division district office to evaluate compliance with
the siting criteria of
19.15.17.10 NMAC. In the absence
of site-specific ground water data, the operator can provide a reasonable
determination of probable ground water depth using data generated by models,
cathodic well lithology, published information or other tools as approved by
the appropriate division district office. The plan for a temporary pit may
incorporate by reference a standard design for multiple temporary pits that the
operator files with the application or has previously filed with the
appropriate division district office. The operator may utilize, with approval
by the appropriate division district office, standardized plans for pit
construction, pit closure, and other plans which will remain approved until a
subsequent plan is either required by the appropriate division district office
or is submitted by the operator and approved by the appropriate division
district office. A copy of the approved standardized plan shall be included in
the division's electronic well file for each associated well.
(3) Below-grade tanks. The registration of a
below-grade tank shall include operating and maintenance procedures, a closure
plan and a hydrogeologic report that demonstrates compliance with the siting
criteria of
19.15.17.10 NMAC. In the absence
of site-specific ground water data, the operator can provide a reasonable
determination of probable ground water depth using data generated by models,
cathodic well lithology, published information or other tools as approved by
the appropriate division district office. The registration of a below-grade
tank may incorporate by reference a standard design for multiple below-grade
tanks that the operator files with the application or has previously filed with
the appropriate division district office. The operator may utilize, with
approval by the appropriate division district office, standardized plans for
below-grade tank construction, and other plans which will remain approved until
a subsequent plan is either required by the appropriate division district
office or is submitted by the operator and approved by the appropriate division
district office. A copy of the approved standardized plan shall be included in
the division's electronic well file for each associated well.
(4) Multi-well fluid management pits. The
design and construction plan for a multi-well fluid management pit shall follow
applicable liner manufacturers' requirements. The permit application also shall
include operating and maintenance procedures, a list of wells with approved
application for permit to drill associated with the pit, a closure plan and
hydrogeologic data that provides sufficient information and detail on the
site's topography, soils, geology, surface hydrology and ground water hydrology
to enable the appropriate division district office to evaluate compliance with
the siting criteria of
19.15.17.10 NMAC. In the absence
of site-specific ground water data, the operator can provide a reasonable
determination of probable ground water depth using data generated by models,
cathodic well lithology, published information or other tools as approved by
the appropriate division district office. The plan for a multi-well fluid
management pit may incorporate by reference a standard design for multiple
fluid management pits that the operator files with the application or has
previously filed with the appropriate division district office. The operator
may utilize, with approval by the appropriate division district office,
standardized plans for pit construction, pit closure, and other plans which
will remain approved until a subsequent plan is either required by the
appropriate division district office or is submitted by the operator and
approved by the appropriate division district office.
C. Filing of permit application.
(1) Permanent pits: An operator shall file an
application on form C-144, including required attachments, with the division's
Santa Fe office to request approval to use or construct a permanent pit and
shall provide a copy to the appropriate division district office.
(2) Temporary pits, and multi-well fluid
management pits. An operator shall file an application on form C-144, including
required attachments, with the appropriate division district office. If the
operator plans to use a temporary pit, or multi-well fluid management pit, the
operator shall provide the proposed pit location on form C-102.