A.
Responsible parties with current ongoing corrective actions/remediation with
approved plans and timelines as of August 14, 2018 do not have to submit
revised plans.
B. Responsible
parties with ongoing corrective actions/remediation without approved timelines
or plans as of August 14, 2018 must submit a characterization plan or
corrective action/remediation plan with proposed timeframes within 90 days of
August 14, 2018.