N.M. Admin. Code § 19.8.5.500 - GENERAL REQUIREMENTS FOR PERMITS: OPERATORS

Except as provided for in Subsection A of 19.8.5.501 NMAC on and after 8 months from the date on which a regulatory program for the state is approved by the secretary of the U.S. department of interior, no person shall engage in or carry out surface coal mining and reclamation operations on non-federal lands within the state, unless that person has first obtained a valid permit issued by the director under the approved program.

Notes

N.M. Admin. Code § 19.8.5.500
11-29-97; 19.8.5.500 NMAC - Rn 19 NMAC 8.2.5.500, 9-29-2000

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.