N.M. Admin. Code § 19.8.5.504 - PERMIT APPLICATION FILING DEADLINES
A. Not later than two (2) months following
approval of the state program by the secretary of the U.S. department of
interior, each person who conducts or expects to conduct surface coal mining
and reclamation operations after the expiration of eight (8) months from that
approval shall file an application for a permit for these operations.
B. Permit renewals and revisions.
(1) An application for renewal of a permit
shall be filed with the director at least 120 days before the expiration of the
permit involved.
(2) Any
application for revision of a permit shall be filed with the director before
the date on which the permittee expects to revise surface coal mining or
reclamation operations. After filing of such application, the director shall
determine the time by which that application shall be approved or disapproved,
based on the time required for review of the application and public
participation in the process of review.
C. Any application for a new permit required
for a person succeeding by transfer, sale, or assignment of rights granted
under a permit shall be filed with the director not later than 30 days after
that succession is approved by the director.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.