(A) Pursuant to the requirements of division
(B) of section 1506.07 of the Revised Code, the
department shall review each application for a permit as described in paragraph
(B) of rule 1506-6-23[1501-6-23] of the Administrative Code to evaluate the
existing or proposed erosion control measures. Factors to be considered in the
evaluation of an erosion control measure shall include, but not be limited to,
the following:
(1) The potential individual
or cumulative impact, including any adverse effects on sand resources and
coastal processes; and
(2) The
potential for accelerating erosion along the adjacent shoreline; and
(3) The stability of the existing or proposed
slope; and
(4) The effectiveness
of existing erosion control measures at the proposed site and along the
adjacent shoreline; and
(5) The
integrity of the existing or proposed erosion control measure, its
appurtenances and component materials; and
(6) The effectiveness of proposed structural
and/or nonstructural measures to protect the permanent structure.
(B) Within thirty days after
receipt of a complete application, the director shall notify the applicant that
the application is either approved or denied. If an application is approved,
the director shall issue a permit, as specified in rule
1501-6-25
of the Administrative Code, to erect, construct, or redevelop the permanent
structure. If an application is denied, the director shall notify the applicant
of the reason for denial and of the applicant's appeal rights under section
1506.08 of the Revised Code.
(C) The director shall issue a
permit to an applicant if:
(1) The proposed
site is or will be protected by effective erosion control measures as
determined according to criteria in paragraphs (A)(1) through (A)(6) of this
rule, or.
(2) Both of the
following criteria are met:
(a) The permanent
structure will be a movable structure or will be situated as far landward as
applicable zoning resolutions or ordinances permit; and
(b) The applicant will suffer exceptional
hardship if the permit is not granted.
(D) Issuance by the director of a permit to
erect, construct or redevelop a permanent structure pursuant to division (B) of
section 1506.07 of the Revised Code does
not release the applicant from obtaining any and all other permits, leases or
documents from any local, state or federal agency for the permanent structure
or for the erosion control measures.
R.C. 119.032 review dates: 07/29/2009 and 07/25/2014
Notes
Rule promulgated under: RC Chapter 119.
Rule authorized by: RC 1506.07
Rule amplifies: RC 1506.07
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.