Ohio Admin. Code 164-1-01 - Definitions
For the purposes of Chapter 164-1 of the Administrative Code:
(A) "Administrator" means the
administrator of the Ohio small government capital improvements commission
appointed under section
164.05 of the Revised
Code.
(B)
"Change order" means a modification of a construction
agreement to provide material or services to the project that were not
specifically delineated in the project agreement or the project
application.
(C)
"Commission" means the Ohio public works
commission.
(D)
"Construction activities" include, but are not limited
to, activities necessary for the erection, demolition, or rehabilitation of the
facilities constituting the project including but not limited to: material
handling (including off-site prefabrication), excavation, land clearance,
demolition, utility relocation, grading, footings, form work, backfill, pipe
installation, facility construction, repair, demolition, and associated
necessary personal services. The work performed may include new work,
additions, alterations, and repairs.
(E)
"Construction
costs" are the costs for construction activities.
(I)
"Engineering costs" are the costs for professional design
and oversight of the project, including related services necessary for
completing the design and assisting the applicant with construction of the
project.
(M)
"Local match" are the funds provided by the applicant
to meet its required participation percentage which may not consist of public
works funds, but may consist of applicant funds, funds received from other
governmental agencies, private lenders, or consist of credits for project
related expenses that the applicant paid or the value of work completed on the
project by the applicant, also referred to as "local subdivision share of the
cost of a capital improvement".
(N)
"Mark-up costs"
are costs above what was incurred by the supplier for personal property or
services purchased from a third-party and invoiced to the
subdivision.
(Q)
"Project
agreement" is an agreement provided for in division (A)(1) of section
164.05 of the Revised Code or
division (B)(1) of section
164.051 of the Revised
Code.
(U)
"Reimbursable prepaids" are project expenses paid by the
applicant within one year of the date of the project agreement.
(X)
"Scope change"
means a substantive alteration of the proposed project.
(CC)
"Workswise portal" is the online access maintained by
the commission for processing applications and all appurtenant information
relating to the programs administered by the
commission.
Notes
Promulgated Under: 119.03
Statutory Authority: 164.05 Chap. 119
Rule Amplifies: 164.01, 164.02, 164.03, 164.04, 164.05, 164.051, 164.06, 164.08, 164.16, 164.20, 164.27
Prior Effective Dates: 06/07/1989 (Emer.), 09/18/1989, 07/18/2013, 09/10/2018
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.