(A)
The university's
bid process for public improvements will follow the state of Ohio's process as
described in the Ohio facilities construction commission manual. The OUA
reserves the right to use Chapter 153. of the Revised Code, competitive bidding
procedures, if there is reasonable concern as to whether the aggregate cost
could exceed the threshold.
(B)
Estimated project
cost below fifty thousand dollars: The OUA project manager shall:
(1)
Obtain quotes
from three contractors, when possible.
(2)
Prepare a
purchase requisition in MagnusMart for the contractor with the lowest
cost.
(3)
Submit request along with the two unused quotes or
non-responses.
(C)
Estimated project cost over fifty thousand dollars, but
below two hundred thousand dollars: the OUA project manager shall:
(1)
Prepare a work
scope defined in a request for quotation.
(2)
Issue the request
for quotation to the selected contractors and publically post the request for
quotation.
(3)
Review responses to request for quotations and
determine apparent lowest responsive and responsible party.
(4)
Create a purchase
requisition in MagnusMart.
(D)
Estimated project
cost over two hundred thousand dollars shall be competitively bid per Chapter
153. of the Revised Code, and, as such, a public bid advertisement is
required.
(E)
See the Ohio facilities construction commission manual
for details on process: http://ofcc.ohio.gov/.
Replaces: 3344-65-27
Notes
Promulgated Under: 111.15
Statutory Authority: 111.15
Rule Amplifies: 3344
Prior Effective Dates: 11/12/13
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.