Ohio Admin. Code 3701-69-13 - Inspections and examinations
(A)
The director may
conduct inspections as he or she considers necessary to determine compliance
with the requirements of this chapter.
(B)
The director
shall examine records of radon testers, mitigation specialists, mitigation
contractors, and operators of approved radon laboratories and training courses
as he or she considers necessary to determine whether they are in compliance
with the requirements of this chapter.
(C)
A licensed radon
tester, mitigation specialist, mitigation contractor, or operator of an
approved radon laboratory or a training course shall make available to the
director any records or equipment pertinent to the activities regulated by this
chapter upon the request of the director.
(D)
The director
shall have the right to test any equipment used for radon testing or
mitigation; to sketch or photograph any portion of a site, building, or
equipment involved in radon testing or mitigation; to copy or photograph any
documents or records pertinent to compliance with this chapter; and to
interview any employees or representatives of the holder of a license or
approval or an applicant for licensure or approval. This right shall not be
conditioned upon any action by the director except presentation of appropriate
identification when requested and compliance with appropriate standard safety
procedures established by the director.
(E)
Upon request of
the director, a licensed radon tester, radon mitigation specialist, or
mitigation contractor or an applicant for licensure shall disclose to the
director the addresses of properties or buildings where radon testing or
mitigation work is scheduled, in progress, or completed and the names of the
owners and residents of the properties or buildings for the purpose of
inspection by the director.
(F)
For the purpose
of compliance inspections, all licensed mitigation contractors shall submit an
electronic report in a form prescribed and provided by the director listing all
mitigation projects completed within the calendar quarter and the following
information for each project:
(1)
Name of occupant, street address, city, county, state
and zip code; of residence where work was done;
(2)
Start and
completion dates;
(3)
Type of radon mitigation system; and
(4)
Pre- and
postmitigation concentrations.
(G)
For the purpose
of compliance inspections, all licensed radon testers and mitigation
specialists shall submit an electronic report in a form prescribed and provided
by the director listing all tests completed within the calendar quarter and the
following information:
(1)
Name of occupant, street address, city, county, state
and zip code of residence where work was done;
(2)
Start and
completion dates;
(3)
Test device used;
(4)
Type of test;
and
(5)
Radon concentration reported.
(H)
The
quarterly reports required in paragraphs (G) and (H) of this rule shall be
submitted electronically and in accordance with the following timelines:
(1)
No later than
April fifteenth for the time period of January first through March
thirty-first;
(2)
No later than July fifteenth for the time period of
April first through June thirtieth;
(3)
No later than
October fifteenth for the time period of July first through September
thirtieth; and
(4)
No later than January fifteenth for the time period of
October first through December thirty-first of the previous year.
Replaces: 3701-69-09
Notes
Promulgated Under: 119.03
Statutory Authority: 3723.09
Rule Amplifies: 3723.08
Prior Effective Dates: 1/1/1992, 7/9/01
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.