Ohio Admin. Code 3745-66-20 - Certification of completion of post-closure care
No later than sixty days after the completion of the
established post-closure care period for each hazardous waste disposal unit,
the owner or operator must submit to the director, by registered mail, a
certification that the post-closure care period for the hazardous waste
disposal unit was performed in accordance with the specifications in the
approved post-closure plan. The certification must be signed by the owner or
operator and an independent registered
independent registered
professional engineer's certification must be furnished to the director upon
request until he releases the owner or operator from the financial assurance
requirements for post-closure care under paragraph (H) of rule
3745-66-45
of the Administrative Code.
Notes
R.C. 119.032 review dates: Exempt
Promulgated Under: 119.03
Statutory Authority: 3734.12
Rule Amplifies: 3734.12
Prior Effective Dates: 04/15/1981, 01/07/1983, 11/13/1987, 04/01/1990,
03/13/2002
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.