Ohio Admin. Code 4901:2-23-05 - Transportation network company permit
(A) Following receipt of a completed
application form submitted by an applicant pursuant to rule
4901:2-23-03 of the
Administrative Code, the staff shall
should issue a permit, provided that the
applicant:
(1) Has affirmed that it will
maintain compliance with the applicable requirements established under sections
4925.03 to
4925.08 of the Revised Code and
with the rules adopted under this chapter; and
(2) Has paid the permit fee in the amount
specified under section
4925.02 of the Revised
Code.
(B) A permit
issued pursuant to this chapter is effective for one year commencing on the
date of issuance.
(C) No less than
thirty days, and no more than sixty days prior to the expiration date of its
permit, a transportation network company shall submit a permit renewal
application form that is substantially the same as the application form
prescribed under rule
4901:2-23-03 of the
Administrative Code. Renewal application forms shall
should be
posted on the commission's website. Following receipt of a completed renewal
application form, the staff shall
should issue a renewed permit provided that the
applicant:
(1) Has affirmed that it will
maintain compliance with the applicable requirements established under sections
4925.03 to
4925.08 of the Revised Code and
with the rules adopted under this chapter; and
(2) Has paid the permit fee in the amount
specified under section
4925.02 of the Revised
Code.
(D) If the staff
does not act upon an application submitted pursuant to paragraph (A) or (C) of
this rule, within thirty days of submission, the application shall be deemed
automatically approved on the thirty-first day after the official filing
date.
(E) If the staff denies
issuance of a permit, or renewal of a permit, for failure of the applicant to
meet the requirements of paragraph (A) or (C) of this rule, staff may serve a
"letter of staff determination" upon the applicant. The letter
shall
should
contain a brief explanation for the denial and instructions regarding the
manner in which the applicant may serve a timely request for an administrative
hearing to contest the denial.
(F)
Within thirty days following service by staff of a letter of staff
determination, the applicant may file a "request for administrative hearing"
with the commission's docketing division in order to contest the denial. The
written request for administrative hearing
contains the name, address, and telephone number of the applicant and is signed
by an authorized representative of the applicant. A copy of the letter of staff
determination should be attached to the request for administrative hearing. All
hearings should be conducted consistent with rule
4901:2-7-16 of the
Administrative Code.
(G) If a
permit renewal application submitted pursuant to paragraph (C) of this rule is
submitted fewer than thirty days prior to the expiration date of the permit, or
after the expiration date of the permit, the applicant may file a motion with
the commission to extend its previous permit during the pendency of staff's
review of the permit renewal application.
(H) No transportation network company may
transfer its permit to another entity without prior approval from the
staff.
Notes
Promulgated Under: 119.03
Statutory Authority: R.C. 4925.02(C)
Rule Amplifies: R.C. 4925.02, 4925.03, 4925.04, 4925.05, 4925.06, 4925.07, 4925.08
Prior Effective Dates: 05/23/2019
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.