Ohio Admin. Code 4906-6-11 - Construction of approved projects and notification of construction
(A) Applicants who file accelerated
certificate applications with the board may begin construction of projects
reported in the applications after the date that automatic approval occurs or
upon the approval by the board.
(B)
Applicants shall file a notice with the board at least seven days in advance of
beginning construction of the involved project if
construction will begin on a different date from that contained in the
application.
(C) Prior to
commencement of construction, the applicant shall inform affected property
owners and tenants
residents of the nature of the project, specific
contact information of applicant personnel who are familiar with the project,
the proposed schedule for project construction and restoration activities, and
a complaint resolution process. Notification to affected property owners and
tenants
residents shall be given at least seven days prior to
work on the affected property.
(D)
Applicants shall file a notice with the board within seven days following
completion of the involved project.
Notes
Promulgated Under: 111.15
Statutory Authority: 4906.03
Rule Amplifies: 4906.03, 4906.06