Ohio Admin. Code 901:9-1-28 - Suspended personnel platforms
(A) Personnel platforms elevated by cranes
which are used as bungee jump platforms shall be constructed and rigged
according to the requirements of
29 CFR
1926.1431 (2010). Where wire rope is used:
(1) Each bridle leg shall be connected to a
master link or shackle;
(2) Wire
rope with thimble eyes shall be used;
(3) Wire rope shall have a safety factor of
five;
(4) Locking load hooks shall
be used;
(5) Gates shall swing
inward and shall be equipped with a latching device that prevents accidental
opening;
(6) The personnel platform
and attaching devices shall have a minimum design factor of five;
(7) The personnel platform shall have a plate
specifying the weight of the empty personnel platform and the maximum number of
persons and weight for which the personnel platform is rated; and
(8) At each new set-up, and at least
annually, prior to hoisting personnel in the suspended personnel platform, the
personnel platform, rigging, and hook block shall be proof tested to one
hundred twenty-five per cent of the personnel platform's rated capacity by
holding it in a suspended position for five minutes with the test load suitably
distributed on the personnel platform. After proof testing, any deficiencies
revealed by inspection by a qualified person shall be corrected and another
proof test shall be conducted. Any modification to personnel platform or
rigging shall require retesting of the personnel platform.
(B) A trial lift with the unoccupied
personnel platform loaded at least to the anticipated liftweight shall be made
from ground level, or any other location where personnel will enter the
platform, to each location at which the personnel platform is to be hoisted and
positioned. This trial lift shall be performed immediately prior to placing
personnel on the platform. The operator shall determine that all systems,
controls and safety devices are activated and functioning properly; that no
interferences exist; and that all configurations necessary to reach those work
locations will allow the operator to remain under the fifty per cent limit of
the hoist's rated capacity. After a trial lift, and just prior to hoisting
personnel, the platform shall be hoisted a few inches and inspected to ensure
that it is secure and properly balanced. Personnel shall not be hoisted unless
the following conditions are determined to exist:
(1) Hoist ropes are free of kinks;
(2) Multiple part lines are not be twisted
around each other;
(3) The primary
attachment is centered over the platform; and
(4) The hoisting system shall be inspected if
the load rope is slack to ensure all ropes are properly seated on drums and in
sheaves.
(C) The jump
rigging shall be attached to the lifting system.
(D) The personnel platform shall be limited
to a capacity of four persons.
(E)
A grab rail shall be provided around the personnel platform.
(F) The sides of the personnel platform shall
be enclosed from floor to midrail as defined under OSHA standards with
rails.
(G) An open roof design of
the personnel platform is optional for better visibility.
(H) Nothing shall be added to the personnel
platform which affects it's stability in the wind.
(I) A jumper shall only jump perpendicular to
the boom.
(J) If the personnel
platform is accidentally lowered onto the cords, the cords shall be inspected
before jumping is continued.
(K) In
addition, all rules and regulations pertaining to the safe hoisting of
personnel as specified by OSHA or other authorities must be complied
with.
Notes
Promulgated Under: 119.03
Statutory Authority: 993.04
Rule Amplifies: 993.04
Prior Effective Dates: 08/27/1992 (Emer.), 12/28/1992, 09/22/2014, 10/21/2019
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.