Okla. Admin. Code § 252:4-7-71 - Water quality time lines

The Water Quality Division shall technically review applications and issue or deny permits within the following periods of time:

(1) Discharges, 401 Certifications, industrial wastewater other than discharge, pretreatment trust users, and sludge management plan - 180 days;
(2) Public water supply and water pollution control construction - 90 days; and
(3) UIC applications - 300 days.

Notes

Okla. Admin. Code § 252:4-7-71
Added at 18 Ok Reg 1922, eff 6-11-01