Okla. Admin. Code § 252:623-11-2 - Reports of changed conditions

Each user must notify the DEQ of any planned significant changes to the user's operations or system which might alter the nature, quality, or volume of its wastewater at least 120 days before the change.

(1) The DEQ may require the user to submit such information as may be deemed necessary to evaluate the changed condition, including the submission of a wastewater discharge permit application under Subchapter 7 of this Chapter.
(2) The DEQ may issue or modify a wastewater discharge permit in response to changed conditions or anticipated changed conditions.
(3) For purposes of this Section, significant changes include, but are not limited to, flow increases of twenty percent (20%) or greater, and the discharge of any previously unreported pollutants.

Notes

Okla. Admin. Code § 252:623-11-2
Added at 18 Ok Reg 1601, eff 6-1-01

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.