Or. Admin. Code § 123-025-0017 - Application Submittal, Review and Approval
(1) An eligible port may submit an
application after consulting with the authority on a preliminary determination
of eligibility and otherwise follow the authority's s procedures for submitting
applications. The application must be in the form provided by the Authority and
must contain or be accompanied by such information as the authority may
require. The authority will process only completed applications.
(2) Upon receipt of a signed application the
authority will within 14 days notify the port as to the status of the
application and advise the port of any missing materials or incomplete
application detail.
(3) Upon
receipt of a completed application the authority will apply the following
criteria to determine the project's eligibility:
(a) The project is cited in or conforms to a
port's adopted strategic business plan required under OAR 123-025-0016 and
approved by the authority and the Peer Review Committee.
(b) The project is not an unnecessary
duplication of marketing efforts among ports. However, it is recognized that
regional or cooperative projects may require ports to simultaneously perform
similar tasks;
(c) The project does
not subsidize regular port operating expenses;
(d) The project will not require or rely upon
continuing subsidies from the authority or department;
(e) Financial need may be a consideration
when reviewing a project proposal for funding; and,
(f) The requirements set out in OAR 123-025
are met. Should cite where these requirements are.
(4) Once an application is considered
complete the authority will, within 60 days approve or reject the
application.
Notes
Stat. Auth.: ORS 285A.075
Stats. Implemented: ORS 285A.654 - 285A.660
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.