Or. Admin. Code § 123-046-0020 - Eligible Project Costs and Activities

Eligible costs include the reasonable costs and necessary, as determined by the Department, for eligible tide gate projects and may include:

(1) Tide gate project development costs including, but not limited to: direct costs associated with design and engineering, legal costs, permitting, environmental review, regulatory processes, landowner coordination, and support activities necessary to develop a tide gate construction project;
(2) Funding award administration costs not to exceed $10,000;
(3) Construction, repair or replacement of tide gates, culverts, or other barriers to land drainage and flood protection associated with a tide gate drainage system;
(4) Support activities necessary to construct a tide gate project;
(5) Activities intended to stabilize drainage channels;
(6) Construction contingencies for a tide gate construction project; and
(7) Financing costs associated with the Department's financing including capitalized interest, issuance and debt service reserve costs, when such costs are incurred in funding a project.

Notes

Or. Admin. Code § 123-046-0020
OBDD 21-2020, temporary adopt filed 10/05/2020, effective 10/5/2020through 4/1/2021; OBDD 4-2021, adopt filed 03/15/2021, effective 3/15/2021

Statutory/Other Authority: ORS 285A.075 & Ch 10, OL 2020

Statutes/Other Implemented: Ch 10, OL 2020