Or. Admin. Code § 137-047-0610 - Notice of Intent to Award
(1)
Notice of Intent to Award. The Contracting Agency shall provide Written notice
of its intent to Award to all Bidders and Proposers pursuant to ORS 279B.135 at
least seven (7) Days before the Award of a Contract, unless the Contracting
Agency determines that circumstances justify prompt execution of the Contract,
in which case the Contracting Agency may provide a shorter notice period. The
Contracting Agency shall document the specific reasons for the shorter notice
period in the Procurement file.
(2)
Finality. The Contracting Agency's Award shall not be final until the later of
the following:
(a) The expiration of the
protest period provided pursuant to OAR 137-047-0740; or
(b) The Contracting Agency provides Written
responses to all timely-filed protests denying the protests and affirming the
Award.
Notes
Stat. Auth.: ORS 279A.065 & 279B.135
Stats. Implemented: ORS 279B.135