Or. Admin. Code § 137-047-0720 - Protests and Judicial Review of Multi-Tiered and Multistep Solicitations
(1) Purpose. An
Affected Offeror may protest exclusion from the Competitive Range or from
subsequent tiers or steps of a solicitation in accordance with the applicable
Solicitation Document. When such a protest is permitted by the Solicitation
Document, then pursuant to ORS 279B.420(3)(f), before seeking judicial review,
an Affected Offeror must file a Written protest with the Contracting Agency and
exhaust all administrative remedies.
(2) Basis for Protest. An Affected Offeror
may protest its exclusion from a tier or step of competition only if the
Offeror is Responsible and submitted a Responsive Offer and but for the
Contracting Agency's mistake in evaluating the Offeror's or other Offerors'
Offers, the protesting Offeror would have been eligible to participate in the
next tier or step of competition. (For example, the protesting Offeror must
claim it is eligible for inclusion in the Competitive Range if all ineligible
higher-scoring Offerors are removed from consideration, and that those
ineligible Offerors are ineligible for inclusion in the Competitive Range
because: their Proposals were not Responsive, or the Contracting Agency
committed a substantial violation of a provision in the Solicitation Document
or of an applicable Procurement statute or administrative rule, and the
protesting Offeror was unfairly evaluated and would have, but for such
substantial violation, been included in the Competitive Range.)
(3) Delivery. Unless otherwise specified in
the Solicitation Document, an Affected Offeror must deliver a Written protest
to the Contracting Agency within seven (7) Days after issuance of the notice of
the Competitive Range or notice of subsequent tiers or steps.
(4) Content of Protest. The Affected
Offeror's protest shall be in Writing and must specify the grounds upon which
the protest is based.
(5)
Contracting Agency Response. The Contracting Agency shall not consider an
Affected Offeror's multi-tiered or multistep solicitation protest submitted
after the timeline established for submitting such protest under this rule, or
such different time period as may be provided in the Solicitation Document. The
Contracting Agency shall issue a Written disposition of the protest in a timely
manner. If the Contracting Agency upholds the protest, in whole or in part, the
Contracting Agency may in its sole discretion either issue an Addendum under
OAR 137-047-0430 reflecting its disposition or cancel the Procurement or
solicitation under 137-047-0660.
(6) Judicial Review. Judicial review of the
Contracting Agency's decision relating to a multi-tiered or multistep
solicitation protest shall be in accordance with ORS 279B.420.
Notes
Stat. Auth.: ORS 279A.065
Stats. Implemented: ORS 279B.060