Or. Admin. Code § 141-089-0650 - General Conditions
The following conditions apply to all general authorizations, unless otherwise specified in a specific GA or an authorization issued under a GA:
(1) Responsible Party. The person
listed on the notification as the responsible party is responsible for the
activities of all contractors or other operators involved in project work
covered by the GA.
(2) Copy of
Approved Notification Available for Inspection. A copy of the notification
approved by the Department must be available at the work site whenever noticed
activities are being conducted.
(3)
Site Access Required. Employees of the Department and all authorized
representatives must be permitted access to the project area at all reasonable
times for the purpose of inspecting work performed under a
notification.
(4) Archeological
Resources. If any archeological sites, resources or artifacts are discovered
during construction, work must immediately cease and the State Historic
Preservation Office must be contacted.
(5) ODFW Fish Passage Requirement. The
activity must meet Oregon Department of Fish and Wildlife requirements for fish
passage before the project is started (ORS 509.580 through 509.901 and OAR
635-412-0005 through 635-412-0040).
(6) Hazards to Recreation, Navigation and
Fishing. The activity must be timed so as not to interfere with or create a
hazard to recreational and commercial navigation and fishing.
(7) Work Period in Jurisdictional Areas. Fill
or removal activities below the Ordinary High Water Line must be conducted when
recommended by ODFW, unless otherwise coordinated with Oregon Department of
Fish and Wildlife and approved in writing by DSL. Work is prohibited when fish
eggs are present within the reach where activities are being
conducted.
(8) Pre-Construction
Resource Area Fencing or Flagging. Prior to any site grading, the boundaries of
any avoided wetlands, waterways and riparian areas adjacent to the project site
must be surrounded by noticeable construction fencing or flagging. There must
be no vegetation removal or heavy equipment within marked areas. The marked
areas must be maintained during construction of the project and be removed
immediately upon project completion.
(9) Erosion Control Methods. The following
erosion control measures must be installed at the construction site prior to
construction and maintained during and after construction to prevent erosion
and minimize movement of soil into waters of this state:
(a) All exposed soils must be stabilized
during and after construction in order to prevent erosion and
sedimentation;
(b) Filter bags,
sediment fences, sediment traps or catch basins, leave strips or berms, or
other measures must be used to prevent movement of soil into waterways and
wetlands;
(c) To prevent erosion,
use of compost berms, impervious materials or other equally effective methods,
must be used to protect soil stockpiled during rain events or when the
stockpile site is not moved or reshaped for more than 48 hours;
(d) Unless part of the permanent fill, all
construction access points through, and staging areas in, riparian and wetland
areas must use removable pads or mats to prevent soil compaction. However, in
some wetland areas under dry summer conditions, this requirement may be waived
upon approval by DSL. At project completion, disturbed areas with soil exposed
by construction activities must be stabilized by mulching and native vegetative
plantings/seeding. Sterile grass may be used instead of native vegetation for
temporary sediment control if native vegetation is unavailable. If soils are to
remain exposed for more than seven days after completion of the permitted work,
they must be covered with erosion control pads, mats or similar erosion control
devices until vegetative stabilization is installed;
(e) Where vegetation is used for erosion
control on slopes steeper than 2:1, tackified seed mulch must be used so the
seed does not wash away before germination and rooting;
(f) Dredged or other excavated material must
be placed on upland areas having stable slopes and must be prevented from
eroding back into waterways and wetlands;
(g) Erosion control measures must be
inspected and maintained as necessary to ensure their continued effectiveness
until soils become stabilized; and
(h) All erosion control structures must be
removed when the project is complete and soils are stabilized and
vegetated.
(10)
Hazardous, Toxic, and Waste Material Handling. Petroleum products, chemicals,
fresh cement, sandblasted material and chipped paint, wood treated with
leachable preservatives or other deleterious waste materials must not be
allowed to enter waters of this state. Machinery refueling is to occur at least
150 feet from waters of this state and confined in a designated area to prevent
spillage into waters of this state. Barges must have a containment system to
effectively prevent petroleum products or other deleterious material from
entering waters of this state. Project-related spills into waters of this state
or onto land with a potential to enter waters of this state must be reported to
the Oregon Emergency Response System (OERS) at 1-800-452-0311.
(11) Raising or Redirecting Water. The
project must not cause water to rise or be redirected and result in damage to
structures or property.
(12) Waste
Disposal. Old piling and other waste material discarded by the project must be
disposed of in an appropriate disposal facility. There must be no temporary
storage of piling or other waste material below top of bank, in any wetland,
Federal Emergency Management Administration designated floodway, or an area
historically subject to landslides.
(13) DSL May Halt or Modify. DSL retains the
authority to temporarily halt or modify the project in case of unforeseen
damage to natural resources.
(14)
Work Area Isolation. The work area must be isolated from the water during
construction. All structures and materials used to isolate the work area must
be removed immediately following construction and water flow returned to
pre-construction conditions. All fish must be salvaged from the isolated area
in accordance with Oregon Department of Fish and Wildlife
requirements.
(15) Spoil Disposal.
Spoil materials, not used in the project, must be placed in an upland location.
Spoil materials used in the project must be included in the cumulative
removal-fill calculation for the activity.
Notes
Statutory/Other Authority: ORS 196.600 - 196.692 & 196.795 - 196.990
Statutes/Other Implemented: ORS 196.600 - 196.692 & 196.795 - 196.990