The following activities are allowed under this general authorization:
(1) Vegetation
Management. Ground-altering activities needed to re-establish and maintain
native vegetation, such as mechanized land clearing to remove non-native
vegetation and disking for seedbed preparation and planting of native wetland
species.
(2) Floodplain Contouring.
Floodplain contouring of wetland terraces to reconnect a waterway to an
adjacent wetland or expand the area of seasonal inundation. This activity does
not include modification of a stream channel.
(3) Microtopography Establishment. Grading
and contouring to re-establish microtopography (hummocks, minor ridges, very
shallow depressions) in areas that have been previously leveled, scalped or
otherwise disturbed to eliminate pre-existing microtopography. Activity is
limited to six-inch maximum elevation rise or drop.
(4) Macrotopography Establishment. Shallow
excavation to create scrapes, basins, meanders and swales that do not exceed
two feet in depth from existing or original ground surface and have minimum
side slopes of 6:1 or gentler. If shallow excavation is combined with berm
construction described in Section 6 of this rule, the maximum depth of
inundation must not exceed two feet.
(5) Removal of Materials. Removal of soil or
other materials that have been placed in a wetland for the purpose of restoring
the natural and/or historical topography.
(6) Low Earthen Berms and Spillways.
Construction of low earthen berms and vegetated spillways that impede, contain
or direct surface water may be used to extend the area or duration of shallow
inundation. The design height of the berms must be no more than 18 inches from
the existing ground level and have a maximum top width of four feet, variable
slopes at a minimum of 6:1 or gentler on the water side, and maximum slopes of
6:1 on the land side, unless gentler slopes do not result in the conversion of
wetland to upland. These structures may be installed to manipulate seasonal
water depth, duration and degree of fluctuation that would be characteristic of
natural or historical hydrologic conditions and to manage invasive species.
When berms are combined with shallow excavation described in Section (4) of
this rule, the maximum depth of inundation must not exceed two feet.
(7) Removal of Structures. Removal of
diversion structures, water control structures, small (three feet high or less)
berms and tidegates, as long as the removal does not cause water to rise or be
redirected in such a manner to result in damage to structures or substantial
property.
Notes
Statutory/Other Authority: ORS 196.600 - 196.692 & 196.795 - 196.990