Or. Admin. Code § 141-093-0151 - Transportation-Related Structures - GP-Specific Conditions
(1) General Conditions Apply. All the
requirements, procedures and conditions set forth in OAR 141-093-0135 apply to
this GP.
(2) Work Area Isolation.
The work area must be isolated from the water during construction. All
structures and materials used to isolate the work area must be removed
immediately following construction and water flow returned to pre-construction
conditions. All fish must be salvaged from the isolated area in accordance with
Oregon Department of Fish and Wildlife requirements.
(3) Proof of Mitigation Purchase. Before an
authorization is approved, the Department must have proof of purchase of
wetland mitigation bank credit, in-lieu fee credit purchase, or cash payment of
the correct in-lieu amount.
Notes
Statutory/Other Authority: ORS 196.600 - 196.692 & 196.795 - 196.990
Statutes/Other Implemented: ORS 196.600 - 196.692 & 196.795 - 196.990